This technology standard is suitable for the general industrial and Civil construction Electrical Installation Projects of ten 6 KV oil paper insulated cable outdoor terminal head production.
2.1.1 Cable terminal head model, specifications should be in line with the voltage level, the use of the environment, and design requirements.
2.1.2 Cable terminal Head, should be supplied by the manufacturers of cable accessories, the main parts, and accessories should be complete, the insulation casing must not have cracks, or damage, and the use of manuals and certificates.
2.1.3 Cable insulation type and voltage level should meet the requirements and should have physical and chemical and electrical performance test sheets and certificates.
2.1.4 Metal fasteners are applied to hot-dip galvanized parts.
2.1.5 Other accessories are a black glass paint belt, sealed lead, stearic acid, copper-stranded wire, white cloth, yellow lead powder, glycerin, petrol, cable oil, and so on.
2.2.1 Production Tools: windproof grid, plastic sheeting, hydraulic connection pliers, blowtorch, iron pot, aluminum pot, enamel plate, aluminum pot, Tieshao, colander, gloves, funnel, electric stove, hacksaw, wire brush, thermometer, scissors and so on.
2.2.2 Installation equipment: pulley, big rope, wrench, bench drill, welding machine, and welding tools.
2.2.3 Test tools: Shaking table, steel tape, steel plate ruler, and test equipment.
2.3.1 Outdoor cable terminations should be made to choose a clear and windy weather construction, ambient temperature above Perin, and the relative humidity of the air is below 70%.
2.3.2 Construction site and its surrounding should be clean and dry, the operating platform to be firm, and April should be the wind fence.
2.3.3 Construction site should be equipped with a 220V power supply and safe power supply.
2.3.4 Construction site should be in line with the safety fire regulations, and flammable materials should be properly kept.
2.3.5 Cable termination and joint production personnel should be specially trained and assessed qualified, can be construction operation.